The 132/33 kV Dual Redundant Power Transmission Line project from Mobin Petrochemical Complex (MPC) to South Pars Gas (Phases 6 & 7 & 8) was held in Asaluyeh County, Bushehr Province by Hirbodan Company in 2006, recommended by Oil Industries Engineering and Construction Co. (OIEC) in the form of EPCC contract.
Scope of Services
- Engineering, Design and Documentation
- Supply of equipment and materials
- Construction
- Commissioning, Pre commissioning & Start-up
- Completing and removing of punch and Defect list
South Pars Gas Field – Phases 6, 7 & 8
Phases 6, 7 & 8 of the South Pars Gas Field located approximately 100km offshore in the Persian Gulf.
The development project for phases 6, 7 & 8 has been designed to produce 104 MMscm/d of gas from the reservoir.
The sour gas produced in these phases is transferred to Aghajari oil field in Khuzestan province via a 512 km pipeline to be injected into the oil wells to enhance the recovery coefficient of the field.
Project Nature
Scope of project is consist of Design, Procurement, Construction, Commissioning and Start-up of 100 MVA, 132/33 kV Dual Redundant Temporary Power Transmission Line from Mobin Petrochemical Complex to South Pars Gas (Phases 6 & 7 & 8).